Water Projects Completed By RAPCO
Sr. No. PROJECT NAME OWNER / LOCATION VALUE (DHS) YEAR ROLE IN PROJECT DETAILS OF PROJECT (Scope of Work)
1 INTERNAL ROADS AND SERVICES FOR SHAWAMEKH CITY
CONTRACT No. 6
PUBLIC WORKS DEPT.ADWEA / ADDC ABU DHABI        14,195,186  WATER WORKS   01.09.01 TO 30.06.02 ROAD CONTRACTOR & WATER WORKS CONTRACTOR WATER RELOCATION WORKS INSIDE ABU DHABI CITY AS PART OF ROAD WIDENING & PARKING CONSTRUCTION WORK.
2 INTERNAL ROADS FOR NEW HOUSES IN SHAWAMEKH CONTRACT No. 4 PUBLIC WORKS DEPT.ADWEA / ADDC ABU DHABI 9,800,500        WATER WORKS 12.12.99 TO 11.03.01 ROAD CONTRACTOR & WATER WORKS CONTRACTOR WATER RELOCATION WORKS INSIDE ABU DHABI CITY AS PART OF ROAD WIDENING & PARKING CONSTRUCTION WORK.
3 INTERNAL ROADS IN SHAWAMEKH CITY EAST, CONTRACT NO. 3 PUBLIC WORKS DEPT., WED-(w) ABU DHABI 4,379,931.21  WATER WORKS 29.04.01 TO 28.02.02 ROAD CONTRACTOR & WATER WORKS CONTRACTOR WATER RELOCATION WORKS INSIDE ABU DHABI CITY AS PART OF ROAD WIDENING & PARKING CONSTRUCTION WORK.
4 INTERNAL ROADS AND SERVICES FOR 30 LOW COST HOUSES AT SWEIHAN PUBLIC WORKS DEPT., WED-(w) ABU DHABI ROAD CONTRACT 16.5 MILLION  WATER WORKS 3,754,638 20.12.98 TO 31.05.99 ROAD CONTRACTOR & WATER WORKS CONTRACTOR WATER RELOCATION WORKS INSIDE ABU DHABI CITY AS PART OF ROAD WIDENING & PARKING CONSTRUCTION WORK.
5 CONSTRUCTION OF INTERNAL ROADS FOR NEW LOW COST HOUSES AT SHAWAMEKH CITY CONTRACT - III PUBLIC WORKS DEPT., WED-(w) ABU DHABI ROAD CONTRACT 81.8 MILLION  WATER WORKS 11,385,427.35 18.8.99 TO 17.11.99 ROAD CONTRACTOR & WATER WORKS CONTRACTOR WATER RELOCATION WORKS INSIDE ABU DHABI CITY AS PART OF ROAD WIDENING & PARKING CONSTRUCTION WORK.
6 INTERNAL ROADS FOR 80 LOW COST HOUSES AT SHAWAMEKH CONTRACT - II PUBLIC WORKS DEPT., WED-(w) ABU DHABI ROAD CONTRACT 26.3 MILLION  WATER WORKS 4,554,642.65 20.04.98 TO 19.04.99 ROAD CONTRACTOR & WATER WORKS CONTRACTOR WATER RELOCATION WORKS INSIDE ABU DHABI CITY AS PART OF ROAD WIDENING & PARKING CONSTRUCTION WORK.
7 TRIP CONTRACT21M IMPROVEMENT OF INTERSECTION & WIDENING OF ZAYED 1ST & 2ND STREET. ABU DHABI MUNICIPALITY       - WED (W) ABU DHABI ROAD CONTRACT 127,949,463 WATER WORKS 11 MILLION 01.05.82 TO 25.03.85 ROAD CONTRACTOR & WATER WORKS CONTRACTOR WATER RELOCATION WORKS INSIDE ABU DHABI CITY AS PART OF ROAD WIDENING & PARKING CONSTRUCTION WORK.
8 TRIP CONTRACT 19  IP-1 INTERCHANGE, UNDERPASS AT ROUND ABOUT, AIRPORT ROAD - ABU DHABI ABU DHABI MUNICIPALITY - WED (W) ABU DHABI ROAD CONTRACT 63,588,000 WATER WORKS 8 MILLION 16.07.83 TO 31.12.85 ROAD CONTRACTOR & WATER WORKS CONTRACTOR WATER RELOCATION WORKS INSIDE ABU DHABI CITY AS PART OF ROAD WIDENING & PARKING CONSTRUCTION WORK.
9 TRIP CONTRACT 76S (JV PAULING (M.V) RAPCO AIRPORT ROAD / EAST ROAD ABU DHABI MUNICIPALITY - WED (W) ABU DHABI ROAD CONTRACT 129,842,000 WATER WORKS 17 MILLION 22.12.85 TO 01.12.86 ROAD CONTRACTOR & WATER WORKS CONTRACTOR WATER RELOCATION WORKS INSIDE ABU DHABI CITY AS PART OF ROAD WIDENING & PARKING CONSTRUCTION WORK.
10 TRIP CONTRACT 14A  SH. KHALIFA BIN SHAKHBUT ST, AL NAHAYAN ST.(SOUTH)ABU DHABI ABU DHABI MUNICIPALITY - WED (W)  ABU DHABI ROAD CONTRACT 113,813,800 WATER WORKS 7 MILLION 10.10.88 TO 13.10.90 ROAD CONTRACTOR & WATER WORKS CONTRACTOR WATER RELOCATION WORKS INSIDE ABU DHABI CITY AS PART OF ROAD WIDENING & PARKING CONSTRUCTION WORK.
11 TRIP CONTRACT 17 / 17A COMBINED KING KHALED BIN ABDEL AZIZ ST. MANHALABU DHABI. ABU DHABI MUNICIPALITY - WED (W) ABU DHABI ROAD CONTRACT 105,971,664 WATER WORKS 18 MILLION 24.09.88 TO 31.12.91 ROAD CONTRACTOR & WATER WORKS CONTRACTOR WATER RELOCATION WORKS INSIDE ABU DHABI CITY AS PART OF ROAD WIDENING & PARKING CONSTRUCTION WORK.
12 TRIP CONTRACT 77 EASTERN RING ROAD(NORTH)ABU DHABI. ABU DHABI MUNICIPALITY - WED (W)  ABU DHABI ROAD CONTRACT 127,281,805 WATER WORKS 8 MILLION 10.11.90 TO 31.05.94 ROAD CONTRACTOR & WATER WORKS CONTRACTOR WATER RELOCATION WORKS INSIDE ABU DHABI CITY AS PART OF ROAD WIDENING & PARKING CONSTRUCTION WORK.
13 TRIP CONTRACT 23  SAEED BIN TAHNOON ST.ABU DHABI ABU DHABI MUNICIPALITY - WED (W)  ABU DHABI ROAD CONTRACT 82,382,636 WATER WORKS 7 MILLION 26.09.92 TO 15.06.95 ROAD CONTRACTOR & WATER WORKS CONTRACTOR WATER RELOCATION WORKS INSIDE ABU DHABI CITY AS PART OF ROAD WIDENING & PARKING CONSTRUCTION WORK.
14 CONTRACT No.1 ABU DHABI - AL AIN EXPRESS WAY ABU DHABI  ABU DHABI MUNICIPALITY  - WED (W) ABU DHABI ROAD CONTRACT 258,390,656 WATER WORKS 33 MILLION 05.01.93 TO 04.01.95 ROAD CONTRACTOR & WATER WORKS CONTRACTOR WATER RELOCATION WORKS INSIDE ABU DHABI CITY AS PART OF ROAD WIDENING & PARKING CONSTRUCTION WORK.
15 TRIP CONTRACT 35TOURIST CLUB AREA WORK INSIDE NAVY COMPOUND  (Utility Ducts, Storm Water System, Kerbs, Asphalt)  ABU DHABI MUNICIPALITY - WED (W)ABU DHABI ROAD CONTRACT 107,870,381.43 WATER WORKS 26,239,957.13 19.06.93 to 30.06.99 ROAD CONTRACTOR & WATER WORKS CONTRACTOR WATER RELOCATION WORKS INSIDE ABU DHABI CITY AS PART OF ROAD WIDENING & PARKING CONSTRUCTION WORK.
16 CONTRACT 950 - SECTOR ROADS E-30, E-34/01, E-34/02, E-35, E-26,  E-28, E-29 & E-39 ABU DHABI MUNICIPALITY - WED (W) ABU DHABI ROAD CONTRACT 61,465,750 WATER WORKS 8,150,895.90 02.11.96 TO 03.05.99 ROAD CONTRACTOR & WATER WORKS CONTRACTOR WATER RELOCATION WORKS INSIDE ABU DHABI CITY AS PART OF ROAD WIDENING & PARKING CONSTRUCTION WORK.
17 CONTRACT 951SECTORS:  W-4, W-9, W-11, W-17/01, W-17/02 & W-17/03 ABU DHABIMUNICIPALITY  - WED (W)  ABU DHABI ROAD CONTRACT 123,704,000 WATER WORKS 14,051,267 04/01/97 TO 04.08.99 ROAD CONTRACTOR & WATER WORKS CONTRACTOR WATER RELOCATION WORKS INSIDE ABU DHABI CITY AS PART OF ROAD WIDENING & PARKING CONSTRUCTION WORK.
18 CONTRACT 302 REHABILITATION & REPLACEMENT OF OLD WATER MAINS (TWIN 900MM) OUTSIDE ABU DHABI ISLAND ADWEA WATER WORKS 51,419,892.10 19/05/01 TO 18.05.03 WATER WORKS CONTRACTOR TWIN 900MM 
DI PIPELINE = 34 KM