| 1 |
ABU DHABI MUNICIPALITY / ADDC |
INTERNAL ROADS IN MUHAMMED BIN ZAYED CITY SECTOR Z-34, CONTRACT NO. 953/4-3 |
M/S. GHANTOOT TRANSP. & GEN. CONT. EST.,M/S. MAUNSELL, ABU DHABI - UAE |
13,999,922.00
12 MONTHS |
100% |
NOT DECIDED |
| 2 |
ABU DHABI MUNICIPALITY / ADDC |
INTERNAL ROADS IN MUHAMMED BIN ZAYED CITY, CONTRACT NO. 953/4-1 |
M/S. GHANTOOT TRANSP. & GEN. CONT. EST., M/S. HALCROW, ABU DHABI - UAE |
23,037,284.07
18 MONTHS |
100% |
NOT DECIDED |
| 3 |
ABU DHABI MUNICIPALITY / ADDC |
INTERNAL ROADS IN MUHAMMED BIN ZAYED CITY, CONTRACT NO. 953/4-2 |
M/S. ADMAK / M/S. HALCROW, ABU DHABI - UAE |
34,445,220.40
18 MONTHS |
100% |
NOT DECIDED |
| TOTAL AMOUNT |
71,482,426.47 |
DHS |
|
|
|
|
|
|
|