| SR. NO. |
NAME OF EMPLOYER |
NAME, LOCATION AND TYPE OF PROJECT |
NAME OF MAIN CONTRACTOR/ CONSULTANT |
CONTRACT PRICE & DATE |
PERCENTAGE OF PARTICIPATION OF COMPANY IN PROJECT |
PROJECT ENDING DATE |
| 1 |
CIVIL DEFENCE |
WATER SUPPLY TO ZAYED MILITARY CITY CONTRACT MW-OU-198-2005 |
M/S. WAAGNER BIRO BIN BUTTI |
6,300,000.00
IN PROGRESS |
100% |
SEP.-06 |
| 2 |
ABU DHABI MUNICIPALITY / ADDC |
INTERNAL ROADS IN SECTOR Z-30, MUHAMMAD BIN ZAYED CITY |
M/S GHNATOOT TRANSP. & GEN. CONT. EST. / M/S MAUNSELL, ABU DHABI, UAE |
12,279,284.00
IN PROGRESS |
100% |
SEP.-06 |
| 3 |
ABU DHABI MUNICIPALITY / ADDC |
COMPLETION OF CONSTRUCTION OF INTERNAL ROADS FOR THE EXTENSION OF KHALIFA CITY 'A' |
M/S GHNATOOT TRANSP. & GEN. CONT. EST. / M/S HALCROW, ABU DHABI, UAE |
21,789,673.00
IN PROGRESS |
100% |
OCTt.-07 |
| 4 |
SUPERVISION COMMITTEE FOR THE EXPANSION OF ABU DHABI - INTERNATIONAL AIRPORT |
WATER & FIRE FIGHTING WORKS, ABU DHABI INT. AIRPORT NEW 2K RUNWAY |
M/S. ODEBRECHT - AL JABER, J.V./ M/S. PARSONS / M/S. HALCROW, ABU DHABI - UAE |
6,496,835.40
IN PROGRESS |
100% |
ACT.-07 |
| TOTAL AMOUNT |
46,865,792.40 |
DHS |
|